NATIONAL HIGHWAY DETAILS

 

S.No.

N.H. no.

Name of National Highway

Length in

Chhattisgarh

(Km.)

Remarks

(Districts covered)

1

6

Dhuliya Nagpur -Raipur Sambalpur

318.40

Mahasamund,Raipur,Durg, Rajnandgaon

2

43

Raipur - Jagdalpur - Vijayanagaram

313.60

Raipur,Durg,Dhamtari,KankerBastar

3

16

Bhopalpattanam - Geedam -
Jagdalpur

217.00

Bastar,Dantewada

4

78

Shahdol Ambikapur –Jashpurnagar -Gumla

354.20

Koriya,Sarguja
Jashpurnagar

5

200

Raipur -Bilaspur Champa -Raigarh-Jharsugda

312.60

Raipur,Durg,Bilaspur
Janjgir,Raigarh

6

202

Haidarabad - Varngal - Bhopalpattanam

36.00

Dantewada

7

12-A

Simga - Kawardha - Chilfi - Mandla

126.00

Raipur,Durg,Kabirdham

8

216

Saraipali - Sarangarh - Raigarh

86.80

Mahasamund.Raigarh

9

217

Arang - Mahasamund -Khariyar Road

65.60

Mahasamund

10

111

Bilaspur-Katghora-Ambikapur

223.00

Bilaspur, Korba, Sarguja

11

221

Jagdalpur-Sukma-Konta

172.00

Bastar, Dantewada

 

 

Total

2225.20

All Districts.

 

 


PROGRESS OF NATIONAL HIGHWAY WORKS 2004-2005

(A) STATUS OF ONGOING NH ROAD WORKS     (As on 6/04 )

                                                                                                                                              (Amount in Rs. Lakhs )

 

S. No.

 

N.H.

No.

 

 

 

NAME OF WORK

 

JOB No.

 

DATE OF SANCT. ORIGINAL &  REVISED

 

SANCTIONED COST ORIGINAL & REVISED

 

LENGTH Km.

EXPENDITURE

STATUS OF WORK AS ON 6/04

UPTO DATE 6/04

 

1

2

3

4

5

6

7

8

9

 

1

 

006

YEAR 1999-2000

Strengthening in Km. 354 to 364 on NH-6

 

006-MP-99-175

 

6.2.2000

 

407.24

355.11

 

11.0

 

346.19

Progress

 

2

 

 

078

YEAR 2001-2002

Improvement & widening of single lane road to two lane road in Km. 502 to 511 of NH-78

 

078-CG-2001-02-13

 

22.5.2001

 

421.71

 

10.0

 

277.39

Progress

 

3

 

200

 

YEAR 2002-2003

Recontruction of 16 Nos. culverts from Km. 8/10 to 77/6 of N.H. 200

 

200-CG-2002-03-66

 

13.3.2003

 

38.00

 

--

 

18.46

 

Progress

 

4

 

 

200

YEAR 2003-2004

Construction of paved shoulder in Km. 117/2 to 118/10

 

200-CG-2003-04-99

 

29.8.2003

 

48.18

 

--

 

--

Tender

 

5

 

12A

 

Construction of H.P. culvert and road side drain in Km. 192/2 to 202

 

12A-CG-2003-04-98

 

29.8.2003

 

46.66

 

--

25.12

 

Complete6/04

6

43

Reconstruction of R.C.C. slab culvert in Km. 164/2

043-CG-2003-04-123

27.2.04

13.83

 

 

Tender

 

 

Total :- 6 Works

 

 

 

 

975.62

 

667.16

1Complete

3 Progress

                                                                                                                                               

 

 

 

 

 

 

 

 

 

 

 

 

(B) STATUS OF ON GOING NH BRIDGE WORKS       (As on 6/04 )

                                                   (Amount in Rs. Lacs)                 

 

 

S. No

 

N.H.

No.

 

 

 

 

NAME OF WORK

 

JOB No.

 

DATE OF SANCT. ORIGINAL &  REVISED

 

SANCTIONED COST ORIGINAL & REVISED

 

LENGTH Km./m

EXPENDITURE

STATUS OF WORK AS ON 6/04

UPTO DATE 6/04

1

2

3

4

5

6

7

8

9

 

 

1

 

 

 

043

Year 2002-2003

 

Reconstruction of H.L. Bridge in Km. 109/10 of N.H. 43

 

 

 

043-CG-2002-03-70

 

 

25.3.2003

 

 

236.20

 

 

--

 

 

124.78

 

 

Progress

 

2

 

06

Year 2003-2004

Reconstruction of H.L. Bridge in Km. 90/6

 

06-CG-2003-04-78

29.8.2003

47.82

--

25.66

Progress

3

043

Construction of H.L. Bridge in 207/10 & approaches

043-CG-2003-04-102

30.12.2003

800.00

--

--

Tender

4

043

Reconstruction of Minor bridge in Km. 160/8 of N.H. 43

043-CG-2003-04-122

25.2.04

86.73

 

 

Tender

5

043

Reconstruction of Minor bridge in Km. 190/6 of N.H. 43

043-CG-2003-04-120

25.2.04

20.08

 

 

Tender

6

216

Reconstruction of Minor bridge in Km. 5/6&7/4 of N.H. 216

216-CG-2003-04-119

25.2.04

61.00

 

 

Progress

 

 

 

Total

 

6 Works.

 

 

 

 

 

1251.83

 

--

 

150.44

 

3 Progres

3 Tender

 


(C) STATUS OF  IRQP (PLAN) PROGRAMME    (As on 6/04 )

                               ( AMOUNT in Rs. Lacs )

S.No.

N.H. No.

NAME OF WORK JOB NO/DATE OF SANCTION

LENGTH (KM)

SANCTONED AMOUNT

DATE OF START

EXPENDITURE UPTO 6/04

STATUS OF WORK AS ON 6/04

1

2

3

4

5

6

7

8

1

006

IRQP in Km. 346 to 353

(Job No. 006-CG-2002-03-61 )

Dt. 19.2.2003

Sanc.No. RW/NH-13012 /2035 / 2002 /CG/NH-5

8.0

268.78

13.5.03

137.12

Progress

2

006

IRQP in Km. 241 to 245,261,264 and 265

(Job No. 006-CG-2003-04-100 )

Dt. 29.8.2003

Sanc.No.  RW/NH-13012/2061/2002/CG/NH-5

8.0

143.06

--

64.95

Progress

 

 

Total :- 2 Works

16.00

411.84

 

202.07

 

3

043

IRQP in Km. 76 to 81

(Job No.043-CG-2003-04-107)

Dt. 19.2.2004

Sanc.No.    RW/NH-12014/360/ 2003/CG/   N H-5

6.0

188.45

 

 

Tender

4

043

IRQP in Km. 82 to 91

(Job No.043-CG-2003-04-108)

Dt. 19.2.2004

Sanc.No.    RW/NH-12014/359/ 2003/CG/   N H-5

10.0

187.50

 

 

Tender

5

043

IRQP in Km. 165,168,177  to 184

(Job No.043-CG-2003-04-89)

Dt. 29.8.2003

Sanc.No. RW/NH-13012/2300/2003/CG/NH-5

10.0

244.59

--

58.14

Complete , liabilities balance

6

043

IRQP in Km. 185 to 190

(Job No.043-CG-2003-04-84)Dt. 29.8.2003Sanc.No. RW/NH-13012/2301/2003/CG/NH-5

6.0

147.84

--

106.38

Complete , liabilities balance

7

043

IRQP in Km. 261 to 271

(Job No.043-CG-2003-04-81)

Dt. 29.8.2003

Sanc.No. RW/NH-13012/2302/2003/CG/NH-5

11.0

200.14

 

 

Tender

8

043

IRQP in Km. 279 to 287

(Job No.043-CG-2003-04-82)

Dt. 30.12.2003

Sanc.No. RW/NH-12014/353/2003/CG/NH-5

9.0

209.52

 

 

Tender

9

043

IRQP in Km. 301 to 306

(JobNo.043-CG-2003-04-103)

Dt. 30.12.2003

Sanc.No. RW/NH-12014/354/2003/CG/NH-5

6.0

142.57

 

 

Tender

 

 

Total :- 7 Works

58.0

1320.61

 

164.52

-

 

10

 

 

016

 

IRQP in Km. 493 to 498  

 (Job No. 016-CG-2003-04-115)

Dt. 20.2.2004

6.0

115.81

-

-

Tender

 

 

Total :- 1 Works

6.0

115.81

 

164.52

-

 

11

 

 

200

 

IRQP in Km. 90/8 to 99  

 (Job No. 200-CG-2002-03-49)

Dt. 21.5.2002

 

9.4

 

189.47

 

15.7.02

 

164.91

Progress

12

200

IRQP in Km. 217 to 226  

(Job No.200-CG-2002-03-67)

Dt. 13.3.2003

Sanc.No. RW/NH-13012/2047/2002/CG/NH-5

10.0

192.24

10.6.03

 

36.55

 

 

Progress

 

13

 

200

IRQP in Km. 150/10 to 164 /2

(Job No.200-CG-2002-03-68)

Dt. 13.3.2003

Sanc.No. RW/NH-13012/2059/2002/CG/NH-5

 

13.4

 

134.56

29.5.03

 

97.47

Progress

14

200

IRQP in Km. 100 to 108

(Job No.200-CG-2002-03-69)

Dt. 13.3.2003

Sanc.No.RW/NH-113012/2017 /2002/CG/NH-5

 

9.0

 

162.20

10.6.03

127.79

Complete

15

200

IRQP in Km. 1 to 9/2

(Job No.200-CG-2002-03-71)

Dt.26.3.2003

Sanc.No RW/NH-13012/ 2290 /2002/CG/NH-5

8.2

267.62

13.5.03

93.19

Progress

16

200

IRQP in Km. 302  to 313

(Job No. 200-CG-2002-03-73 )

Dt. 31.3.2003

Sanc.No. NH-13012/2305/2002/CG/NH-5

12.0

191.63

10.6.03

71.64

Progress

17

200

IRQP in Km. 227 to 236/4

(Job No. 200-CG-2002-03-75 )

Dt. 31.3.2003

Sanc.No NH-13012/2048/2002/CG/NH-5

9.4

130.68

29.5.03

31.18

Progress

18

200

 I.R.Q.P Km. 243/6 to 258/4

(Job No. 200-CG-2003-04-121 )

Dt. 24-2-04

Sanc.NoSRW/NH-12014/26/2003/CG/N H-5

14.80

342.12

 

 

Tender

19

200

IRQP in Km. 207/4 to216 (Old)

(Job No. 200-CG-2002-03-77 )

Dt. 31.3.2003

Sanc.No.NH-13012/2057/2002/CG/NH-5

9.8

188.40

10.6.03

 

Progress

20

200

IRQP in Km. 116/10 to127/6

(Job No. 200-CG-2002-03-54 )

Dt. 31.5.2002

Sanc.No.NH-13012/2067/2002/CG/NH-5

 

10.8

 

 

 

 

 

 

 

203.96

16.8.02

144.54

Progress

21

200

IRQP in Km. 109 to116/8

(Job No. 200-CG-2002-03-42 )

Dt. 18.6.2002

Sanc.No.NH-13012/2015/2002/CG/NH-5

 

 

 

7.8

 

 

 

 

 

 

200.25

14.8.02

159.59

Complete

22

200

IRQP in Km. 140 to 150/8 &176 to 178

(Job No. 200-CG-2003-4 114 )

Dt. 20.2.2004

Sanc.No.NH-12014/464/2003/CG/NH-5

13.80

204.43

 

 

Tender

 

 

 

Total :- 12 Works

 

 

128.40

 

2407.56

 

 

1036.56

-

23

12A

IRQP in Km. 224 to 231             (Job No. 12A-CG-2003-04-105)

Dt. 30.12.03

Sanc.No NH-13012/229/2003/CG/NH-5

8

207.07

--

--

Tender

24

12A

IRQP in Km. 232 to 241/7             (Job No. 12A-CG-2003-04-101)

Dt. 30.12.03

 

9.7

182.92

--

--

Tender

 

 

 

Total 2 Works

 

17.70

 

389.99

 

--

 

-

-

25

078

IRQP in Km. 297 to 303

(Job No. 078-CG-2003-04-95 )

Dt. 29.8.2003

Sanc.NoRW/NH-12014/346/2003/CG/NH-5

7.0

146.04

 

40.00

Work in progress

26

078

IRQP in Km. 288 to 296

(Job No. 078-CG-2003-04-104 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/344/2003/CG/NH-5

9.0

138.17

-

-

Tender

27

078

IRQP in Km. 314 to 321

(Job No. 078-CG-2003-04-86 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/347/2003/CG/ NH-5

8.0

168.39

-

-

Tender

28

078

IRQP in Km. 322 to 331

(Job No. 078-CG-2003-04-80)

Dt. 30.12.2003

Sanc.NoRW/NH-12014/345/2003/CG/N H-5

10.0

161.83

 

23.2.04

--

Work in Progress

29

078

IRQP in Km. 340 to 346

(Job No. 078-CG-2003-04-91 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/338/2003/CG/ NH-5

7.0

152.13

-

--

Tender

30

078

IRQP in Km. 347 to 354

(Job No. 078-CG-2003-04-87 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/331/2003/CG/ NH-5

8.0

132.95

-

--

Tender

31

078

IRQP in Km. 374/5 to 377/5

(Job No. 078-CG-2003-04-90 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/387/2003/CG/ NH-5

3.0

77.68

26.05.04

--

Work in Progress

32

078

IRQP in Km. 391/8 to 400

(Job No. 078-CG-2003-04-85 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/332/2003/CG/ NH-5

9.4

155.77

--

--

Tender

33

078

IRQP in Km. 453 to 462

(Job No. 078-CG-2003-04-92 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/341/2003/CG/ NH-5

10.0

104.68

27.02.04

--

In Progress

34

078

IRQP in Km. 514 to 517 & 556 to 560/4

(Job No. 078-CG-2003-04-97 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/342/2003/CG/ NH-5

8.4

111.58

 

--

Tender

35

078

IRQP in Km. 543 to 555      (Job No. 078-CG-2003-04-106 )

Sanc.NoSRW/NH-12014/340/2003/CG/ NH-5 Dt. 30.12.2003

13.0

179.49

 

--

Tender

36

078

IRQP in Km. 557 to 566

(Job No. 078-CG-2003-04-93 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/337/2003/CG/ NH-5

10.0

155.45

 

--

Tender

37

078

IRQP in Km. 577 to 584

(Job No. 078-CG-2003-04-94 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/330/2003/CG/ NH-5

8.0

131.29

 

--

Tender

38

078

IRQP in Km. 332 to 339

(Job No. 078-CG-2003-04-116 )

Dt. 25.02.2004

Sanc.NoRW/NH-12014/330/2003/CG/ NH-5

8.0

220.79

 

--

Tender

39

078

IRQP in Km. 443 to 452

(Job No. 078-CG-2003-04-117 )

Dt. 25.02.2004

Sanc.NoRW/NH-12014/330/2003/CG/ NH-5

10.0

291.33

 

--

Tender

40

078

IRQP in Km. 567 to 576

(Job No. 078-CG-2003-04-118 )

Dt. 25.02.2004

Sanc.NoRW/NH-12014/330/2003/CG/ NH-5

10.0

282.46

 

--

Tender

 

 

Total :- 16 Works

138.80

2610.03

 

40.00

-

41

216

IRQP in Km. 32 to 40

(Job No. 216-CG-2003-04-88 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/217/2003/CG/ NH-5

9.2

146.84

 

--

In Progress

42

216

IRQP in Km. 51 to 66

(Job No. 216-CG-2003-04-83 )

Dt. 30.12.2003

Sanc.NoRW/NH-12014/320/2003/CG/ NH-5

16.0

269.67

 

 

Tender

43

216

IRQP in Km. 41 to 50

(Job No. 216-CG-2003-04-109 )

Dt. 19.02.2004

Sanc.NoRW/NH-12014/320/2003/CG/ NH-5

10.0

161.75

 

 

Tender

44

216

IRQP in Km. 76/8 to 83

(Job No. 216-CG-2003-04-110 )

Dt. 19.02.2004

Sanc.NoRW/NH-12014/320/2003/CG/ NH-5

7.21

178.83

 

 

Tender

45

216

IRQP in Km. 84 to 91/6

(Job No. 216-CG-2003-04-124 )

Dt. 26.02.2004

Sanc.NoRW/NH-12014/320/2003/CG/ NH-5

7.42

187.63

 

 

Tender

 

 

Total :- 5 Works

49.83

944.72

 

 

-

46

217

IRQP in Km. 36 to 46

(Job No. 217-CG-2003-04-111 )

Dt. 19.02.2004

Sanc.NoRW/NH-12014/320/2003/CG/ NH-5

11.0

241.62

 

 

Tender

47

217

IRQP in Km. 47 to 55

(Job No. 217-CG-2003-04-113 )

Dt. 19.02.2004

Sanc.NoRW/NH-12014/320/2003/CG/ NH-5

9.0

208.88

 

 

Tender

48

217

IRQP in Km. 56 to 66/6

(Job No. 217-CG-2003-04-112 )

Dt. 19.02.2004

Sanc.NoRW/NH-12014/320/2003/CG/ NH-5

10.45

216.22

 

 

Tender

 

 

Total :- 3 Works

30.45

666.72

 

 

-

 

 

Grand Total :- 48 Works

445.18

8867.28

 

1443.15

 

                 

 

 

 

 

 

(D) STATUS OF P.R. (NON-PLAN)  PROGRAMME

 

(Amount in Rs. Lacs) As on 06/2004

 

S.No.

N.H. No.

NAME OF WORK JOB NO/DATE OF SANCTION

LENGTH (KM)

SANCTONED AMOUNT

DATE OF START

EXPENDITURE UPTO 06/04

STATUS OF WORK AS ON 06/04

1

2

3

4

5

6

7

8

 

1.

 

 

043

 

PR in Km. 116  to 125             (TA-043-CG-2003-04-48)        Dt. 31.12.2003

 

 

10.0

 

186.80

-

-

Tender

 

2

043

PR in Km. 126 to 137  (Ex. Km.127)   (TA-043-CG-2003-04-49)        Dt. 31.12.2003

 

11.0

193.31

-

-

Tender

 

 

Total :-  2 Nos.

21.0

380.11

 

-

-

3

016

PR in Km. 499 to 504             (TA-016-CG-2003-04-47)        Dt.31.12.2003

 

6.0

108.12

-

-

Tender

 

 

Total :- 1 Nos.

6.0

108.12

 

-

-

 

 

Grand  Total :- 3 Nos.

27.0

488.23

 

-

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(E) STATUS OF OTHER F.D.R. (CONTINUOUS) WORKS

(Amount in Rs. Lacs)

Sr. No.

Name of Work

TA No.

Date

Sanctioned Amount

Date of commence

ment

Expenditure upto

Status of work as on

 

 

JUNE 2004

JUNE 2004

1

2

3

4

5

6

7

8

1

FDR  work of NH Div. No. 2 Raipur

 (2003-04)

TA No. 200-12A-CG-2003-04-52

12.02.04

29.67

-

26.50

Complete

2

FDR  work of NH Div. No. 1 Raipur

 (2003-04)

 

TA No. 6,43,216 & 217-CG-2003-04-53

12.02.04

84.41

-

75.97

Complete

3

FDR  work of NH Div. Jagdalpur

 (2003-04)

 

TA No. 43-CG-2003-04-51

12.02.04

25.21

-

61.50

Complete

4

FDR  work of NH Div. Bilaspur

 (2003-04)

 

TA No. 200-CG-2003-04-54

12.02.04

34.33

-

77.80

Complete

5

FDR  work of NH Div. Ambikapur (2003-04)

 

TA No. 78-CG-2003-04-50

12.02.04

85.37

-

124.68

Complete

6

FDR  work of NH Div. 2 Raipur

 (2003-04)

 

TA No. 200,12A-CG-2003-04-56

31.03.04

181.22

-

-

Tender

7

FDR  work of NH Div. 1 Raipur

 (2003-04)

 

TA No. 6, 43,216,217-CG-2003-04-55

31.03.04

67.36

-

-

Tender

8

FDR  work of NH Div. Jagdalpur

(2003-04)

 

TA No. 43-CG-2003-04-58

31.03.04

31.78

-

-

Tender

9

FDR  work of NH Div. Ambikapur (2003-04)

 

TA No. 78-CG-2003-04-57

31.03.04

241.55

-

-

Tender

 

 

Total :-

 

780.90

 

366.45

5 Complete

4 Tender